The Continuous Journey

The Muchisso School- 2/3 Complete!!

A Brighter Future for 3,000 Students

Muchisso School is home to 3,000 eager learners, many of whom have been studying under trees, exposed to the elements. Thanks to our dedicated partners over 3000 students will now have access to fully equipped classrooms, complete with desks and chairs generously provided by the
Canadian High Commission in Maputo.


Our Vision for the Future

Additional supports such as a gymnasium/community centre and library, will be constructed as a final stage of the project if funds permit.
We’ve done it before—this is our third successful project in Mozambique—and with your generosity, we know we can do it again!

DONATE TODAY

Phase I
2019 - 2020 Construction of Sanitary Block

·       Project Budget: $111,855.73 Cdn (4,927.965.18 Meticais)  
·       Funding Source: Muchisso School District, Distrito da Matola, Provincia de Maputo

*As a sign of support for Steven's Hope's commitment to fund the construction of the Muchisso School, the Ministry of Education committed to constructing a block of washrooms, which was completed in 2020. Unfortunately, given the vast need for school facilities throughout the region, the Ministry of Education is not in a position to fund any more projects on the site.

Phase II
2021-2022 Construction of Classroom Block

·       Project Budget: $70,180.00 Cdn (3,091,883.84 Mt)  

·       Funding Sources: Steven's Hope (Rotary Club of Edmonton Gateway - $60,000.00)

·       Donation: Canadian High Commission ($10,000.00)  

Phase III
2023-2024 Construction of Security Wall

·      Wall
·      Security Building
·      Barbed wire
·      Gate
·      Plaster & Painting

Estimated Project Budget (unfunded): $100,000.00 CDN*

Tender will be issued once sufficient funds have been raised. Currently, $10,000.00 CND has been raised for the first phase.

*Project will be completed in phases, in accordance with the funds raised. Based on previous experience, revised specs and a formal tendering process, anticipating the budget for the wall can be substantively reduced.

Phase IV
Additional Classroom Blocks & Washroom Blocks

Timeline: 2023 -2025

Phase IV consists of construction site preparation, three classroom blocks and an additional washroom block.

Estimated budget for the classroom/washroom construction project is approximately $285,000.00 CDN.

2019 - 2020
Phase I
COMPLETED

Sanitary Block Built

Estimate: 
$111,855.73
2021 - 2022
Phase II
COMPLETED
Classroom Block Built
Estimate: 
$70,180.00
2023 - 2025
Phase III
FUNDRAISING GOAL AT 95%

Security Fence

& Maintenance for Macambucuine Campus

Estimate: 
$23,000.00
2025 - 2027
Phase IV
PROJECTED

Additional Classrooms and Washroom Blocks for Muchisso Campus

Estimate: 
approx. $90,000.00 CND

Sanitary Block Built

Estimate: 
$111,855.73
2019 - 2020
Phase I
COMPLETED
Classroom Block Built
Estimate: 
$70,180.00
2021 - 2022
Phase II
COMPLETED

Security Fence

& Maintenance for Macambucuine Campus

Estimate: 
$23,000.00
2023 - 2025
Phase III
FUNDRAISING GOAL AT 95%

Additional Classrooms and Washroom Blocks for Muchisso Campus

Estimate: 
approx. $90,000.00 CND
2025 - 2027
Phase IV
PROJECTED