The Continuous Journey

3 Schools, But We're Not Done!
Macambacuine Campus, Pussa School and Muchisso School need continued Support!

Steven's Hope, in collaboration with Mozambique partners, have plans to add an additional block of 3 classrooms to our most recent school project: Muchisso.
As well, a MAINTENANCE PLAN is being designed for all three schools. Ensuring the safety, security and longevity of these schools for generations of students to come!


Have a peek at the fantastic progress on the construction of the Muchisso School Project!
Check out more about the Fall 2023 visit to the schools in Lorne's Blog
Phase I
2019 - 2020 Construction of Sanitary Block

·       Project Budget: $111,855.73 Cdn (4,927.965.18 Meticais)  
·       Funding Source: Muchisso School District, Distrito da Matola, Provincia de Maputo

*As a sign of support for Steven's Hope's commitment to fund the construction of the Muchisso School, the Ministry of Education committed to constructing a block of washrooms, which was completed in 2020. Unfortunately, given the vast need for school facilities throughout the region, the Ministry of Education is not in a position to fund any more projects on the site.

Phase II
2021-2022 Construction of Classroom Block

·       Project Budget: $70,180.00 Cdn (3,091,883.84 Mt)  

·       Funding Sources: Steven's Hope (Rotary Club of Edmonton Gateway - $60,000.00)

·       Donation: Canadian High Commission ($10,000.00)  

Phase III
2023-2024 Construction of Security Wall

·      Wall
·      Security Building
·      Barbed wire
·      Gate
·      Plaster & Painting

Estimated Project Budget (unfunded): $100,000.00 CDN*

Tender will be issued once sufficient funds have been raised. Currently, $10,000.00 CND has been raised for the first phase.

*Project will be completed in phases, in accordance with the funds raised. Based on previous experience, revised specs and a formal tendering process, anticipating the budget for the wall can be substantively reduced.

Phase IV
Additional Classroom Blocks & Washroom Blocks

Timeline: 2023 -2025

Phase IV consists of construction site preparation, three classroom blocks and an additional washroom block.

Estimated budget for the classroom/washroom construction project is approximately $285,000.00 CDN.

2019 - 2020
Phase I
COMPLETED

Sanitary Block Built

Estimate: 
$111,855.73
2021 - 2022
Phase II
COMPLETED
Classroom Block Built
Estimate: 
$70,180.00
2023 - 2024
Phase III
FUNDRAISING GOAL AT 75%

Additional Classroom Blocks

Estimate: 
$45,000.00
2023 - 2025
Phase IV
PROJECTED

Security Fence & Additional Supports

Estimate: 
approx. $285,000.00 CND

Sanitary Block Built

Estimate: 
$111,855.73
2019 - 2020
Phase I
COMPLETED
Classroom Block Built
Estimate: 
$70,180.00
2021 - 2022
Phase II
COMPLETED

Additional Classroom Blocks

Estimate: 
$45,000.00
2023 - 2024
Phase III
FUNDRAISING GOAL AT 75%

Security Fence & Additional Supports

Estimate: 
approx. $285,000.00 CND
2023 - 2025
Phase IV
PROJECTED